DHC wants to thank Fourmidable for their several years of service to our Parkside residents and welcome Continental as our new property manager.
September 25, 2024 Wednesday, September 25, 2024, at 6:00 P.M. in the Parkside Community Center building (5000 Conner St, Detroit, MI 48213) No zoom will be available for this meeting. The session will be interactive and must be attended in person. |
Parkside Redevelopment
The Villages at Parkside is a 52-acre public housing project on the east side of Detroit. Parkside is located at the northeast corner of E Warren Ave and Conner St, and is located immediately across the street from the historic Chandler Park. DHC is partnering with Ginosko Development Company to redevelop Parkside as a new residential community with a broad mix of housing options across several affordable income ranges. Part of the project involves converting Parkside from Low Income Public Housing (Section 9) funding to Section 8 funding, which is more stable and predictable. This will happen through a HUD program called RAD, which stands for Rental Assistance Demonstration.
DHC and Ginosko want residents and stakeholders to understand fully what will happen at the property. The project team strongly encourages any residents and stakeholders with questions about the project to submit them to parkside@dhcmi.org –or alternatively, residents can reach out to the Resident Representatives for help submitting questions.
Please browse the material below to understand this redevelopment effort and to learn about about ongoing community engagement. Please note that DHC and Ginosko plan to hold several community engagement events at Parkside for this project. Some of the meetings are required as part of the RAD program, but several meetings are being held with the primary goal of keeping residents up-to-date.
A binder is available in the lobby of the community center for residents to review RAD-related information, including the Resident Information Notice (RIN) and General Information Notice (GIN). Additionally, we strongly encourage residents to review the RAD Fact Sheets available on the HUD website. For instance, Fact Sheet #9 has useful information on RAD and Relocation.
If you need materials in a language other than English, please send us an email.
Si necesita materiales en un idioma diferente al inglés, por favor envíenos un correo electrónico.
Si vous avez besoin de documents dans une autre langue que l'anglais, veuillez nous envoyer un e-mail.
إذا كنتم بحاجة إلى مواد بلغة غير الإنجليزية، يرجى إرسال بريد إلكتروني إلينا
যদি আপনি ইংরেজি ছাড়া অন্য ভাষায় উপকরণ প্রয়োজন, দয়া করে আমাদের ইমেল করুন।
Jeśli potrzebujesz materiałów w innym języku niż angielski, prosimy o wysłanie do nas e-maila.
如果您需要非英语的材料,请给我们发送电子邮件。
Timeline of Anticipated Project Milestones
Please note that the dates in this timeline are subject to change.
-
2024
- Begin architectural and engineering ("A&E") design
- Begin conducting environmental investigations to prepare HUD- and EGLE-required reports
- Secure Board approval to enter into a Development Agreement with Ginosko
-
2025
-
Q1-Q2: Ribbon Cutting – Construction activities begin
-
-
2026
- July: Construction completion and ready for move-ins
- Summer (Q2 - Q3): residents relocate to new buildings; demolition activities would soon follow